SPLOST IV PROJECT DECRIPTIONS

TIER I

SANITARY SEWER-'K' STREET
Install Sanitary Sewer and Storm Drains on "K" Street from Newcastle to US Hwy 17. This includes installation of new lines on Macon Street and Talmadge Street. Currently, lines are inadequate to carry loads, and may be required to carry flow from St. Simons Island in the near future. With the installation of these lines it will eliminate Lift Stations 15, 16, 18, and 19, therefore reducing associated maintenance costs. $4,650,000

15" GRAVITY SEWER-DIXVILLE
Install a Sanitary Gravity Sewer line and storm drainage in this area. This will eliminate all known septic tanks in the southend area, remove sewer lines from alleys and improve all storm drainage. $2,425,000

30" GRAVITY SEWER
Install a Gravity Sewer from Reynolds Street at Fifth Street to Lift Station #35 in the Arco area. The existing gravity sewer is inadequate from current flows and flows are projected to increase due to development in the I-95 Interchange area. $ 535,000

SLUDGE DRIER
Install a Sludge Drier that is compatible with the existing composting process and equipment located at the Wastewater Treatment Plant. This will reduce amendment requirements and maintenance costs at the Compost Facility, and eliminate hauling and manpower requirements. $1,750,000

GRAVITY SEWER-FLETC
Install a northend Gravity line, which replaces portions of the 27"/42" Gravity Sewer from FLETC to Second Street at Reynolds Street. The existing lines vary in size and will not be adequate to handle projected flows from the Branniger Tract and PAWS Project. $2,000,000

ARCO 12" WATER MAIN
Install a water main from Ninth Street at Newcastle Street to Ross Road and north to Austin Street along US Hwy 341. This will provide adequate water service and fire protection to the Arco Area of Glynn County by looping Austin Street. This area currently has inadequate water pressure for maximum fire protection.
$ 400,000

STORM DRAIN-HOWE STREET
Install Storm Drainage structures on Howe Street from Albany Street to Bay Street, including floodgates. This project will also include Georgia Street at Egmont Street and Ellis Street. The existing Storm Drainage system is inadequate to handle normal storms. This includes drainage of Glynn Academy High School. Once completed, system will be upgraded to handle a 25-year storm. $1,500,000

CITY HALLS (NEWCASTLE STREET AND GLOUCESTER STREET)
To complete current remodeling at Old City Hall and the New City Hall. Cost has exceeded SPLOST III Funds set aside to complete work. $ 800,000

TOTAL FOR TIER I:     $14,060,000



SPLOST IV PROJECT DESCRIPTIONS TIER II & III

SANITARY SEWER-'K' STREET
Continuation from Tier I. $3,000,000

THE RITZ THEATER
This project will be to renovate the facade and second and third floors of the Theater. By doing this, it will bring the floors up to code and provide a more useful space. $1,700,000

WATER RECLAMATION PROJECT
This is for installation of a Pumping Station and a 2-inch line from Academy Creek Wastewater Treatment Plant to Georgia Pacific Plant to pipe effluent for use as cooling water. This will allow GP to decrease Floridian Aquifer withdrawal and allow the City to increase water withdrawal permit quantity. $1,410,000

STORM DRAIN - 'N' STREET
Install Storm Drainage structures on "N" Street from Norwich Street east to the Hercules property line. Project to include replacement of a portion of line extending under the Adult Education Center with an exterior line. The existing storm drain system is inadequate to handle normal storms. System is to be upgraded to handle a 25-year storm. Line under Adult Education Center is in a state of failure. $1,750,000

PUBLIC SAFETY COMPLEX
To provide a feasibility study of construction of a multi-story Public Safety Complex at another location and to renovate current headquarters on Mansfield Street for additional offices. The present facility is too small, below FEMA flood plain level, and does not conform to ADA requirements. $ 750,000

PUBLIC WORKS COMPLEX
Construct a complete Public Works Complex suitable for handling the day-to-day operations of City Services, including land acquisition. Current operations are spread throughout the City making communications difficult and data sharing impossible. This would pool resources for several operating divisions of government and make many smaller parcels of land available for private investment. $3,750,000

WATER/WASTEWATER COMPLEX
Construct a complete Water and Wastewater Complex. This will be constructed concurrently and as a part of the Public Works Complex. Current operations are spread throughout the City making communications and data sharing impossible. This would pool resources for several operating divisions of government and make many smaller parcels of land available for private investment. $1,500,000

SIDEWALKS
Install and replace torn up sidewalks in all Town Common areas. This will improve the safety and convenience of all pedestrians. $ 85,000

MULTI-PURPOSE CENTER UPGRADE
Install new ceiling tiles, paint and carpet. Remodel arts center and construct a driveway. This will improve the safety and convenience of all pedestrians attending the Center. $ 175,000

STREET PAVING
Paving of any dirt streets and roads remaining in the City that are approximately one-mile in length. This will provide better access for emergency and service vehicles, and reduce drainage problems. $ 190,000

TOTAL FOR TIER II & III PROJECTS:     $14,310,000

GRAND TOTAL FOR SPLOST IV PROJECTS:     $28,370,000

<< Home



Administration | City Attorney | City Clerk | City Commission | Community Development
Contact Info | Engineering | Finance | Fire | Human Resources
Information Technology | Municipal Court | Parks & Recreation | Police | Public Works
Purchasing | Resources & Links | Home

EMAIL EMPLOYEES ONLY

City of Brunswick, Georgia © 2008 All Rights Reserved • a bluemoon website